OK Laz. I presume you created the hammock task in the Gantt Chat view?
Right
click the Start Date and select Clear Contents. Ditto with the Finish Date.
It's likely Mike is off-line. To answer your question, choose Edit >
Links to show the Links dialog box. Select the link and click the Break
Link button. You'll need to break the link to the Start as well as the
Finish.