I
Ivan
I am trying to create traffic light icons at the Project
Server level to inform management of projects that are
either over-budget or off schedule. I have been able to
easily create a formula at the task level to calculate
this using baseline and plan data, but have not been able
to apply a similar formula at the Project Center level.
I have created two Enterprise Project Number fields and
created a formula comparing Baseline Cost and Baseline
Finish Dates to Cost and Finish Date and using an IIF
statement defined three answers of 1, 2, or 3 but when I
look at the individual projects this info does not appear
at the Project Center level.
Does anyone know how to create automatic Traffic Lights at
the Project Center level. I can create manual ones, but I
want the determiniation made by a formula and not by the
pm. Any ideas?
Thanks
Ivan
Server level to inform management of projects that are
either over-budget or off schedule. I have been able to
easily create a formula at the task level to calculate
this using baseline and plan data, but have not been able
to apply a similar formula at the Project Center level.
I have created two Enterprise Project Number fields and
created a formula comparing Baseline Cost and Baseline
Finish Dates to Cost and Finish Date and using an IIF
statement defined three answers of 1, 2, or 3 but when I
look at the individual projects this info does not appear
at the Project Center level.
Does anyone know how to create automatic Traffic Lights at
the Project Center level. I can create manual ones, but I
want the determiniation made by a formula and not by the
pm. Any ideas?
Thanks
Ivan