Budget Resources - Do they work in Server 2007

J

john

It appears that the Budget Resources are causing these erros. It looks like
we are not going to be able to use this feature. SP1 did not address this.

Is anyone using the Budget Resource feature in Project Server 2007
successfully?

Thx
J
 
B

Ben Howard

I spent some time looking at this and decided not to use it as it wasn't
mature/rich enough for my client. I also discovered a bug if you weren't
entering work in hours. However, other than that bug (which hasn't been
fixed in SP1 or the SP1 roll up) it worked fine, in its limited way.
 
J

john

Hi Ben,

Thanks for the reply. We are using the actual work method by using the
timesheet and importing the timesheet into our tasksand submitting them to
the PMs. I guess we will have to create a custom Budget Number or Cost field.

Thx
J
 
P

Paul Conroy

Hi Ben,

Has the rollup been released, or do you have access to a preview ?

Paul
 
Top