Is there a way to put in a 3 day buffer between projects automatically? We have weekend work so I can't use that as any sort of buffer.
 
Joined
Jun 26, 2023
Messages
6
Reaction score
0
Is this on one project file or two?

If it's in one project file, any reason why you can't add 3 days lag between a project completion and project start milestone?
 