E
Ed
We're using Project Server 2002.
We're trying to maintain interdepencies between projects.
The proposed method was as follows:
- Create Milestones in both projects (predecessor and
successor)
- Create a Predecessor link fro the successor project to
the task in the predecessor project
- copy the %Complete from the Predecessor Task and PASTE
LINK to the successor Task milestone.
This provides us with the ability to:
- see in the predecessor column the name of the
predecessor project
- get auto updates of the dates AND %Complete from the
Predecessor Task to the Successor project's milestone.
PROBLEM:
- Although the dates update using the predecessor
reference of the form <>\predproject\##
- the PASTE LINK of the %Complete generates an error...
(See below)
+++
"my project" contains linked information.
Do you want to reestablish the links?
Hit Yes
Microsoft Project cannot connect to link "<>\My link
Project"
Do you want to delete the link?...
+++
All we really want is a way of propogating,
automatically, the marking of the predecessor's %Complete
updates to the Successor Projects.
Any help here would be greatly appreciated...
Ed
We're trying to maintain interdepencies between projects.
The proposed method was as follows:
- Create Milestones in both projects (predecessor and
successor)
- Create a Predecessor link fro the successor project to
the task in the predecessor project
- copy the %Complete from the Predecessor Task and PASTE
LINK to the successor Task milestone.
This provides us with the ability to:
- see in the predecessor column the name of the
predecessor project
- get auto updates of the dates AND %Complete from the
Predecessor Task to the Successor project's milestone.
PROBLEM:
- Although the dates update using the predecessor
reference of the form <>\predproject\##
- the PASTE LINK of the %Complete generates an error...
(See below)
+++
"my project" contains linked information.
Do you want to reestablish the links?
Hit Yes
Microsoft Project cannot connect to link "<>\My link
Project"
Do you want to delete the link?...
+++
All we really want is a way of propogating,
automatically, the marking of the predecessor's %Complete
updates to the Successor Projects.
Any help here would be greatly appreciated...
Ed