Bulk Resource Substitution in Project Server 2007

E

egoncharov

Which is the best way to do bulk resource substituoun?

For example, a user is a resource in many projects. He is retired. A project
manager must substitute this resource with another one. Is there any way to
do it automatically? I mean the Project Manager chooses projects in which the
resource is assigned to tasks and substitutes them with another resource.
 
D

Dale Howard [MVP]

egoncharov --

No, there is no automated way to perform the resource substitution, even
using the Resource Substitution Wizard. The PM needs to open each project
and manually substitute the new resource for the former resource. The
fastest way to do this would be to click Tools - Build Team from Enterprise
and use the Replace feature in the Build Team dialog. Alternately, the PM
can also use the Replace feature in the Assign Resources dialog. Hope this
helps.
 
Top