Burn rate

M

Michael Vestel

Is there a way to show the costing based on assigned resouces in a month by
month fashion. We call this burn rate and i'm trying to show the total cost
per month for the entire project. seems possbile, but not sure what to look
under in the help. tried burn rate but there is nothing. Any quick pointers
are great. thansk.
 
J

Jan De Messemaeker

Task Usage view or Resource Usage view, set minor timescale to Months.
HTH
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top