We are new to using earned value in Project and have numerous projects with
pre-exisitng baselines. After setting up the std and ovr rates for all
resources I find I must establish a "new" baeline to get the BCWS & BCWP to
calculate. Is there a way to force the calculation against the exisitng
baseline?