D
DonD
Is there a way that Project can calculate the Duration for a task (and hence
for the entire work plan) based on the 'Optimistic' Work estimates for each
of the resources assigned to the task?
It as though I'd like to replicate what is currently happening with the Work
& Duration fields.
Hypothetically the 'Optimistic' Work estimate could be stored in the Number1
field, and the 'Optimistic' Duration could be stored in the Duration1 field.
for the entire work plan) based on the 'Optimistic' Work estimates for each
of the resources assigned to the task?
It as though I'd like to replicate what is currently happening with the Work
& Duration fields.
Hypothetically the 'Optimistic' Work estimate could be stored in the Number1
field, and the 'Optimistic' Duration could be stored in the Duration1 field.