J
James_0159
Can Anyone help,
I want to be able to calculate easily the difference btwn two date and times,
eg:
start - 21-Jan-2004 07:30
finish - 22-Jan-2004 06:30
the answer I want to see is 23 hours.
If the times are less than 24 hrs I don't have an issue, but if the shutdown
goes over 24 hours I have some difficulties calculating. In reality if I only
enter the start and finish times I really want to see the actual durations.
eg:
Start - 07:30
Finish - 06:30
If the shut finishes on the next day at 06:30 it should calculate out at
23Hrs.
I want to be able to calculate easily the difference btwn two date and times,
eg:
start - 21-Jan-2004 07:30
finish - 22-Jan-2004 06:30
the answer I want to see is 23 hours.
If the times are less than 24 hrs I don't have an issue, but if the shutdown
goes over 24 hours I have some difficulties calculating. In reality if I only
enter the start and finish times I really want to see the actual durations.
eg:
Start - 07:30
Finish - 06:30
If the shut finishes on the next day at 06:30 it should calculate out at
23Hrs.