calculate

E

ellebelle

i have a very large project file. it is significantly faster when i turn the
calculation off (under options). however, sometimes it would be good to
calculate a single selected row/s only instead of having to calculate the
entire project. is this possible?
 
R

Rob Schneider

Sorry, it's all or nothing.

I'm surprised you really notice the computation time. It must be really
big or you have a slow computer.

With such a big and clearly important file, you are taking measures to
make backups of versions at frequent intervals, I hope.


--rms

www.rmschneider.com
 
A

Andrew Lavinsky

To add to Rob's point, you could perhaps consider a macro to calculate a
single line. In fact, to speed things up, you may want to consider moving a
number of your custom field calculations to a macro - thus allowing you to
use automatic calculations for some fields but run the macro for specific
batches of fields.
 
E

ellebelle

i have an incredibly fast compueter but i am runnning a schedule for 800
people and many, many thousands of tasks. i clear out my historical stuff
regularly.

i think the macro advice is the way forward. i will see if i can find
something on the net. pls let me know if you see something that could work. i
am no coder.

thanks!
 
R

Rob Schneider

Trevor's point is excellent. I'm also curious what you mean by "clear
out my historical stuff regularly". Is this a Project file of a project?
We don't normally "clear out" stuff and instead just finish projects
(hopefully) and stop using the file. Could there be some unintended
consequences caused by the "clear out"?

--rms

www.rmschneider.com
 