Mark Hafner
Can I write a formula in for the Duration field that will enter in the work
value plus a move time. For example: ((Qty*Hrs per unit)+Move time in
hours)= Duration
Currently I am doing this is a custom field but then after all my changes I
have to go back and enter in the calculated fiel into the duration field
manually. I am sure this is the wrong way.
Thanks
Mark