G
Greg
I see this in the help file.
How can I view this field?
If I select insert column, I cannot find the Pessimistic Duration field.
thanks
Pessimistic Duration (task field) The Pessimistic Duration field
contains the worst-case possibility for the total span of active working
time expected for a task, that is, the time from the pessimistic start to
the pessimistic finish of a task. You can enter this date as part of a PERT
analysis calculation.
How can I view this field?
If I select insert column, I cannot find the Pessimistic Duration field.
thanks
Pessimistic Duration (task field) The Pessimistic Duration field
contains the worst-case possibility for the total span of active working
time expected for a task, that is, the time from the pessimistic start to
the pessimistic finish of a task. You can enter this date as part of a PERT
analysis calculation.