Pessimistic Duration field

G

Greg

I see this in the help file.
How can I view this field?
If I select insert column, I cannot find the Pessimistic Duration field.
thanks


Pessimistic Duration (task field) The Pessimistic Duration field
contains the worst-case possibility for the total span of active working
time expected for a task, that is, the time from the pessimistic start to
the pessimistic finish of a task. You can enter this date as part of a PERT
analysis calculation.
 
R

Rod Gill

If you display the Analysis Toolbar, then click the PERT Analysis button it
displays a PERT Toolbar. On here is a Pessimistic Gantt that re-uses
Duration3 for pessimistic durations. The PERT Entry sheet button is where
you enter the data.

--

Rod Gill
Microsoft MVP for Project - http://www.project-systems.co.nz

Author of the only book on Project VBA, see: http://www.projectvbabook.com




Greg said:
I see this in the help file.
How can I view this field?
If I select insert column, I cannot find the Pessimistic Duration field.
thanks


Pessimistic Duration (task field) The Pessimistic Duration field
contains the worst-case possibility for the total span of active working
time expected for a task, that is, the time from the pessimistic start to
the pessimistic finish of a task. You can enter this date as part of a
PERT analysis calculation.


__________ Information from ESET Smart Security, version of virus
signature database 5029 (20100414) __________

The message was checked by ESET Smart Security.

http://www.eset.com

__________ Information from ESET Smart Security, version of virus signature database 5029 (20100414) __________

The message was checked by ESET Smart Security.

http://www.eset.com
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top