P
Pat
I must be doing something wrong. I am the Administrator and I have a
project mgr who needs a 24 hour calendar on some tasks in his project.
The 24 hr calendar is indicated on the task but doesn't that mean the
resources assigned must have a 24 hr calendar too? I have given this
Project Mgr the same rights as a Resource Manager to change working
time. He will change the calendar for the resource, save the project
and close. When he reopens the project the resource calendars are set
back to Standard. How can we schedule a task with assigned resources
to work a different schedule?
project mgr who needs a 24 hour calendar on some tasks in his project.
The 24 hr calendar is indicated on the task but doesn't that mean the
resources assigned must have a 24 hr calendar too? I have given this
Project Mgr the same rights as a Resource Manager to change working
time. He will change the calendar for the resource, save the project
and close. When he reopens the project the resource calendars are set
back to Standard. How can we schedule a task with assigned resources
to work a different schedule?