I am fairly new to Microsoft Project, I know the basics about entering into
the Gantt Chart.
What I am looking for is I enter dates and tasks in the Gantt Chart but I
have added a column called "Status Of" which I customized to have a Value
List of "Green, Yellow, Red and Gray". 2 things with this 1) when I select a
value in the Gantt Chart View it doesn't show up in the project column but it
does up in the formula bar area. 2) If the "Status Of" thing works, in the
Calendar View I would like the bar color coded to the Value (Green, Yellow,
Red or Gray) - is this possible?
Thanks!
Stacey
the Gantt Chart.
What I am looking for is I enter dates and tasks in the Gantt Chart but I
have added a column called "Status Of" which I customized to have a Value
List of "Green, Yellow, Red and Gray". 2 things with this 1) when I select a
value in the Gantt Chart View it doesn't show up in the project column but it
does up in the formula bar area. 2) If the "Status Of" thing works, in the
Calendar View I would like the bar color coded to the Value (Green, Yellow,
Red or Gray) - is this possible?
Thanks!