Calendar creation permissions in Project Server 2003

V

Victoria

Hi,
I know that Administrators can create custom calendars that can be applied
to the global template. Is there a particular permission that allows this
right?

thanks,
V.
 
D

Dale Howard [MVP]

Victoria --

There is no specific permission that allows a user to create custom
Calendars in the Enterprise Global. Rather, if a user has the Save
Enterprise Global permissions, he/she can check out and edit the Enterprise
Global file. This means that the user can create all types of enterprise
objects in the Enterprise Global file, including custom Fields, Views,
Tables, Filters, Groups, and even Calendars. Hope this helps.
 