Calendar display

B

Buzzy

In my current situation, our time is tracked in two week
intervals. From the 1st - 15th, and the 16th - EOM.
(28,30,31) I have project set up in two week intervals,
but the calendar display in the PWA, is shown from Sunday
to the second Saturday. Is there any way I can get the
calendar to display 1-15, and 16-EOM? I have looked
everywhere, and any help at all would be appreciated.

Thanks,
Buzz
 
G

Gary L. Chefetz [MVP]

Buzz:

It sounds like you're trying to apply a semi-monthly payroll construct to
your project management platform. If you're attempting this for the purpose
of pushing the data to a payroll system, your best approach is to collect
the hours by day and worry about consolidating the data into semi-monthly
periods when you do your extract query.
 