A
aes262
Hi,
I've changed my standard calendar to be 4 hours per day however MSP isn't
reflecting this in it's calculations.
Also, I've created a non-standard calendar for a resource (called her name)
which MSP doesn't appear to be recognising as it is allocating deliverables
on non-work days (she works 3 days per week).
Am I missing something?
Thanks
I've changed my standard calendar to be 4 hours per day however MSP isn't
reflecting this in it's calculations.
Also, I've created a non-standard calendar for a resource (called her name)
which MSP doesn't appear to be recognising as it is allocating deliverables
on non-work days (she works 3 days per week).
Am I missing something?
Thanks