Calendar

J

Jerome Ranch

I've been having probelsm with this for awhile..its time to solve it
with your help (since I'm not getting anywhere myself)

My projects involve growing plants. Plants have a 24/7 workday, how
do I set this up in my project calendar

Thanks
Jerry
 
S

Steve House

Do the plants do work in your project? I assume you mean plants as in
vegetable organisms, not factories. <grin> The calendars fundamentally
deal with the hours during which work is performed by people.
 
J

Jerome Ranch

Well, my "staff" are plants Steve
When you say that a plant reaches pollination stage in 90 days, one
doesn't mean a 9-5 job, and exclude weekends.
When one has to sychronize materials (for pollination, transplant,
etc, each step is well timed), Project can do a good job of helping
you plan

Jerry
 