J
Jeroen
Hello
I set up my standart calender with workday from 08:15-12:30 / 13:00-16:45.
When i link a resource to this calender and to the tasks.
I made a test with a week with every day one task with one day
duration. Now the first day is start 28-04-2008 / 08:15 and end
28-04-2008 / 16:45. The other day gave me start 29-04-2008 / 08:00 and
end 29-04-2008 / 17:00 (and so on with the other days).
Why ar not all the days from 08:15 - 16:45? And how can i change it?
I set up my standart calender with workday from 08:15-12:30 / 13:00-16:45.
When i link a resource to this calender and to the tasks.
I made a test with a week with every day one task with one day
duration. Now the first day is start 28-04-2008 / 08:15 and end
28-04-2008 / 16:45. The other day gave me start 29-04-2008 / 08:00 and
end 29-04-2008 / 17:00 (and so on with the other days).
Why ar not all the days from 08:15 - 16:45? And how can i change it?