Excellent....I think this will work out
Thank yo
----- John Beamish wrote: ----
Although the task begins in Stage1, it is not, technically, a Stage1 task
since it does not have to be completed to gate through to Stage2
Therefore, you could do the following
1. Use a plan that has a summary task for each stage and, within that
summary task you will find only those sub-tasks where completion is a
requirement for that stage's gate plus two milestone tasks (more on that
in a moment)
2. Tasks like the one you describe may *begin* in stage1 but the related
"gate" is in stage2 so tasks like this are really sub-tasks within the
stage2 summary task
3. The final subtask in stage1 is a milestone: "Gate exit approved"
4. The second (you'll see in a moment why it could be the third or
fourth) subtask in stage2 is a milestone. "Stage entry"
5. Link those two milestones
6. The task you are having problems with is the first sub-task in
Stage2. It is guaranteed to start earlier than the "Stage Entry"
milestone so the Stage2 summary task will also begin earlier. Note that
you can have lots of these tasks ... just put them ahead of the "Stage
Entry" milestone (and, of course, establish proper linkages)
So ... what have we done
1. When a Stage's summary task is complete ... the final milestone for
that stage has been completed ("Gate exit approved")
2. A subsequent stage's summary task may be partially completed even
before a preceeding summary task is complete because we are now accurately
showing task(s) that can be started early but which still must be
completed before the stage's exit gate can be reached
3. We have linked the stages by "hanging" tasks within a stage from the
"Stage entry" milestone and we have linked that starting milestone to the
exiting milestone of the previous stage
JLB, PM
On Thu, 26 Feb 2004 10:21:07 -0800, Scott
We are currently implementing MS Project for a stage/gate process. The
issue that we are running into is that we have tasks that span multiple
stages and are gated later on in the project
stage1 but ends in stage2. It is not a requirement that the task be
complete in stage1 to enter into stage2. How can this be modeled in MS
Project? We do want to show that stage1 is complete therefore the
summary needs to be correct for reporting
--