H
Hunter
Help!!!
Task Fixed Cost $2,730.00
Resource1
Resource2
Resource3
I have a task with a fixed cost. I have 3 resources assigned. I want to
track the actual hours of the resources but not their costs. When the task
is completed, we will pay 70% of the fixed cost now and 30% when the project
is completed. How do I do this. Project wants to put the $ towards the
resouces. If I manually add $1911 (70%) the remaining cost does not reflect
the 30% left. Can project do this?
Any help would be greatly appreciated.
Thanks,
Hunter
Task Fixed Cost $2,730.00
Resource1
Resource2
Resource3
I have a task with a fixed cost. I have 3 resources assigned. I want to
track the actual hours of the resources but not their costs. When the task
is completed, we will pay 70% of the fixed cost now and 30% when the project
is completed. How do I do this. Project wants to put the $ towards the
resouces. If I manually add $1911 (70%) the remaining cost does not reflect
the 30% left. Can project do this?
Any help would be greatly appreciated.
Thanks,
Hunter