Can a resource manager fill time sheet for his/her employees and h

R

Ramana Vakka

Hi,

We are in the beginning stages of implementing project server and want to
have managers fill in the work completed via PWA instead of engineers.

What mechanisms are available in 2003?

thanks
--ramana
 
D

Dale Howard [MVP]

Ramana --

If you are using the Hours of Work Done Per Day or Per Week method of
tracking progress, your RM's can use the Adjust Actuals feature for this
purpose. Otherwise, no, this cannot be done. Hope this helps.
 
R

Ramana Vakka

Dale,

Thanks for pointing this option.

Our RMs are updating by task completion % - since this is not possible to
update actual % my question is -

Is there a way to see the planned work also in the adjust actuals view?

--ramana
 
D

Dale Howard [MVP]

Ramana --

No, this is not possible. The RM's can see planned work, however, using the
View Resource Assignments option in the sidepane on the left side of the
Resource Center page. Hope this helps.
 