C
Chris Molland
Hello,
I would be grateful if someone could explain how to perform the following
(if it can be done at all!)
I wish to prepare a selection of library Projects, each with a few Tasks and
their associated Resources etc. Perhaps these could be saved as Templates. I
then will create a Master project file and insert items from my library. I
have called these sub-projects.
If I insert a sub-project which when defined had 3 Tasks and the total
duration for the sub-project was, for example, 4 days - can I select the
sub-project and override the total duration to 6 days. In effect stretching
the individual Tasks proportionally?
I want to allow a user to pick from the library sub-projects which have been
pre-defined in terms of Tasks and Resources but allow a global stretch or
shrink of the sub-project duration based on experience at the time it is
inserted into the Master project file.
Thank you.
I would be grateful if someone could explain how to perform the following
(if it can be done at all!)
I wish to prepare a selection of library Projects, each with a few Tasks and
their associated Resources etc. Perhaps these could be saved as Templates. I
then will create a Master project file and insert items from my library. I
have called these sub-projects.
If I insert a sub-project which when defined had 3 Tasks and the total
duration for the sub-project was, for example, 4 days - can I select the
sub-project and override the total duration to 6 days. In effect stretching
the individual Tasks proportionally?
I want to allow a user to pick from the library sub-projects which have been
pre-defined in terms of Tasks and Resources but allow a global stretch or
shrink of the sub-project duration based on experience at the time it is
inserted into the Master project file.
Thank you.