Can A Sub Project's Duration Be Changed?

C

Chris Molland

Hello,

I would be grateful if someone could explain how to perform the following
(if it can be done at all!)

I wish to prepare a selection of library Projects, each with a few Tasks and
their associated Resources etc. Perhaps these could be saved as Templates. I
then will create a Master project file and insert items from my library. I
have called these sub-projects.

If I insert a sub-project which when defined had 3 Tasks and the total
duration for the sub-project was, for example, 4 days - can I select the
sub-project and override the total duration to 6 days. In effect stretching
the individual Tasks proportionally?

I want to allow a user to pick from the library sub-projects which have been
pre-defined in terms of Tasks and Resources but allow a global stretch or
shrink of the sub-project duration based on experience at the time it is
inserted into the Master project file.

Thank you.
 
J

Jack Dahlgren

To change the project duration, you need to adjust the individual tasks. The
summary reflects the durations of the tasks below it.

-Jack Dahlgren
 