Can I add predecessors in a master project file?

D

Donal P

I have a master project file with five sub-projects embedded in it. In the
sub-tasks I would like to reference, as predecessors, some of the tasks
carried in the master file itself.

The ID column repeats itself, so I get random results when I try to show as
a predecessor a task from the master file using the ID value.

Is there any way to make this work? Thanks in advance.

Donal
 
M

meg99

I have a master project file with five sub-projects embedded in it.  Inthe
sub-tasks I would like to reference, as predecessors, some of the tasks
carried in the master file itself.  

The ID column repeats itself, so I get random results when I try to show as
a predecessor a task from the master file using the ID value.  

Is there any way to make this work?  Thanks in advance.

Donal

Select the task that will be the Predecessor.
Hold down the Ctrl key and then find the task that will be the
Succcessor
Let go of the Ctrl Key
then do either of these:
In main menu, Edit, link tasks
Press the link icon
Press Ctl+F2


meg 99
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top