Can I apply a bell curve to work for a task

G

Guest

Is there any way in project to apply a non straight line loading to a task
in project? Like a bell curve or other variable work per week without
breaking up the task?
 
C

Chris Marriott

Hi Rob

You can apply many profiles to tasks in project without breaking up the task
itself

Go to the "task usage" view

Double click on the task - this will bring up the "Assignment Information"
dialog box which has a drop down value list with contouring options - which
includes bell

Hope this helps


--
Regards


Chris Marriott - PMP MCSE MCDBA
UK - EPM Consultant & Trainer
 