can i group resources into teams in Project 2000

I

Ian Louth

I need to have individual named resources and then assign these individuals
into teams. Is this achievable in Microsoft Project 2000
 
J

Jan De Messemaeker

Hi,

Not out of the box, sorry.
One could imagine VBA programming to do it, but not standard :-(
 
P

Peter Rooney

Ian,

I had a similar problem - I have a multi project plan, on which 19
resources, split into four teams may work. Have you tried inserting a new
field into your plan, renaming it as (somewhat imaginatively) "Team", and
entering "Team01", "Team02" etc into this field?
This is also really useful when you want to filter your plan to show just
the work carried out by a particular team or teams.

Hope this helps

Pete
 