A
Anonymous Coward
I have a final milestone task of zero duration that is the successor
of set of tasks, let's say tasks 10, 11, ..., 50. Task "milestone" is
done when all task 10-50 are done (just an example). Can I somehow
state that the predecessors for "milestone" are tasks 10-50 or 10:50
rather than 10, 11, 12, ..., 48, 49, 50?
If I must enumerate the tasks with commas, let me ask a variant
question. Each of the tasks are identified with an integer. Is
there a way to state predecessors as tags, like 'doX', 'doY' and
'doZ'? And state the predessors that way, rather than long lists of
integers?
Thanks.
of set of tasks, let's say tasks 10, 11, ..., 50. Task "milestone" is
done when all task 10-50 are done (just an example). Can I somehow
state that the predecessors for "milestone" are tasks 10-50 or 10:50
rather than 10, 11, 12, ..., 48, 49, 50?
If I must enumerate the tasks with commas, let me ask a variant
question. Each of the tasks are identified with an integer. Is
there a way to state predecessors as tags, like 'doX', 'doY' and
'doZ'? And state the predessors that way, rather than long lists of
integers?
Thanks.