Can I know who has edited my project ?

R

Rachel

I had published a project into the server, however
realised later that some of the tasks had been amended.
How can I know who is the culprit as a few of the account
users had administrative rights or project managers
rights ? Will the person who edited my project been shown
somewhere ??

Thanks,
Rachel
 
G

Gary L. Chefetz [MVP]

Rachel:

The name of the last person to save the plan is stored in the database. In
2002, saving the plan automatically changes the owner (I think this may be a
bug) of the plan to the last person saving it. Therefore, you can see who
last saved the plan by going to the Project Center in Project Web Access,
and select the project and click the Edit Project Details button on the tool
bar.
 