Can I set up a summary for CRITICAL TASKS only in Project 2003?

R

Rod Gill

Not as such. However, you can group tasks based on critical or not. Select
Project, Group By, Critical
 
P

Prj_Mngr

You could add the Critical field to your view and auto filter anything that
has a Yes in the field
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top