Can Project operate on daily scale?

H

Haitao

I need to schedule a project on daily scale as apposed to
hourly scale. In other words, I don't need to worry about
different hours in a day. The minimum time scale is 'a
day'. Could anybody tell me how this can be done? Thanks!
 
R

Rod Gill

Are you seeing dates and times in the start and finish columns? If so,
select Tools, Options and select a date format that doesn't show time.
Project will still calculate to the nearest minute, you just won't see the
time.

--
Rod Gill
Project MVP
For Microsoft Project companion projects, best practices and Project VBA
development services
visit www.projectlearning.com/
 