If I have one request of the Project world it is that there is
eventually a clear universally
accepted notion that Resources can be people, teams, robots, machines,
bacteria etc.
The fact that the ones that can't report for themselves must have agents
to do it for them, does
not mean they can't stand alone or in groups; that they do not have
profound effects on Project
outcomes and in know way should they have to suffer levels of
abstraction as to their productivity.
(100% is absolute.). I would never schedule or plan anything in other
than a 24 hour project calendar.
It makes no sense and only works if you are willing to accept a large
amount of variation
in you resource availability or restriction to the application of them.
"Steve House [Project MVP]" <
[email protected]>
wrote in message 100% means the resource is working full speed and every minute of time
worked is being converted to 1 minute's worth of work output. So in a
24 hour day it is physically impossible for a resource working 100% to
do more than 24 man-hours of work. On the other hand, a resource that
is a collective group of workers - say a custodial staff that has 5
people whom you have chosen not to differentiate by name in your
resource list - CAN generate more than 1 hour of work output for every
hour of work time put in. In this instance you would show "custodians"
as your resource and with 5 of them on staff your Maximum Allocation
entry would be 500%. A resource is overallocated when they go over the
designated maximum. So if you assigned 3 custodians to the task and it
had an 8 hours duration, you would assign them at 300% and the result
would be their performing 24 man-hours of work over the course of an 8
hour task duration. You won't get red flagged until you go over the
500% defined maximum - that marks the overallocation becausethat
assignment says that every available person is fully comitted to this
task and you have no more resources who could be assigned. OTOH, if
you assigned at 300% while leaving the maximum allocation in the
resource definitions at 100%, you'd get red flagged as overallocated
because what you're telling Project is that you have only have one warm
body available and yet you're going to put them on a task and expect
them to do the work of 3 people. Hardly a reasonable expectation.
I have a problem with setting the calendar to reflect a 22.5 hour
workday. To do so means that a single individual resource, Joe Worker,
once he starts on a task will work on it continuously, day and night,
only taking a total of an hour and a half out of every 24 for sleep and
meals and time with his family, potentially for weeks at a time, until
that task is done. Again, that is hardly a reasonable thing to expect
out of your workers. People simply aren't capable of that grueling a
work schedule. I'm going to assume that your real situdation is
something more reasonable - a group of workers who cover different
shifts and collectively they cover the 24 hours of the day. Assume for
discussion a shift is 8 hours plus an hour for lunch. You would create
not one but 3 calendars - Days (8am-5pm), Swing (3pm-12m), Grave
(11pm-8am). If you had 15 custodians equally divided around the clock,
create 3 resource groups, Day Custodians 500%, Swing Custodians 500%,
and Grave Custodians and assign each collective resource the
appropriate calendar that describes their shift. You have a task that
is going to run around the clock for 2 24 days and requires 3
custodians per shift. Assign Day Cust @ 300%, 48 hours work, Swing Cust
300% 48 hours work, Grave Cust 300% 48 hours work. Task duration will
be 48 hours and if it starts Monday at 8am it will end Wed at 8am. That
will result in a total 9 different custodians, 3 per shift, working a
total of 2 days, all of them doing 2 8 hour shifts each, a much more
humane schedule with a total of 144 man-hours of work being generated
and probably closer to what your resources really are doing.
--
Steve House [MVP]
MS Project Trainer & Consultant
Visit
http://www.mvps.org/project/faqs.htm for the FAQs
message Is there a way I can set a resource to work 90hours/day? We are
combining a
few different resources and need it to show that when we put 100% of a
resource to something it is putting 90 hours a day toward it. Now we
are
setting it at 22.5 hours/day, and putting 400% towards the tasks to
give us
90 hours per day, but it shows up as being 300% overallocated in the
Resource
Graphs and reports. Thank you.