T
Ted
I have read through many posts trying to find my question previously
answered. Unfortunately, if it's there I simply have not found it yet.
MS Project 2000
When I level a resource on either daily or weekly basis, it gets
overallocated.
I understand that overallocated means all allotted units for a resource are
assigned to multiple tasks that may occur at the same time or overlap.
Therefore, 100% units on 2 4-hour tasks will show as 200% allocated, even
though the total number of hours doesn't exceed an 8 hour working day.
However, in my case, my resources DO get leveled with more hours than are
available in the day or week. I have one resource, for example, who is the
only resource working on two different tasks. Those two tasks each are 40
hours of effort (work).
When I level that resource on a daily basis, these two tasks are schedule on
the same week. Although each task doesn't take more than 8 hours each day,
the two tasks sum to 16 hours of work for the day.
I do not have a resources assigned to summary tasks.
All constraints are "As soon as possible"
All resources use the standard calendar which is set up for 8 hour days.
All task types are fixed work, effort driven
"Can Level" is set to YES only for the resource being leveled.
I would sincerely appreciate your ideas and suggestions.
answered. Unfortunately, if it's there I simply have not found it yet.
MS Project 2000
When I level a resource on either daily or weekly basis, it gets
overallocated.
I understand that overallocated means all allotted units for a resource are
assigned to multiple tasks that may occur at the same time or overlap.
Therefore, 100% units on 2 4-hour tasks will show as 200% allocated, even
though the total number of hours doesn't exceed an 8 hour working day.
However, in my case, my resources DO get leveled with more hours than are
available in the day or week. I have one resource, for example, who is the
only resource working on two different tasks. Those two tasks each are 40
hours of effort (work).
When I level that resource on a daily basis, these two tasks are schedule on
the same week. Although each task doesn't take more than 8 hours each day,
the two tasks sum to 16 hours of work for the day.
I do not have a resources assigned to summary tasks.
All constraints are "As soon as possible"
All resources use the standard calendar which is set up for 8 hour days.
All task types are fixed work, effort driven
"Can Level" is set to YES only for the resource being leveled.
I would sincerely appreciate your ideas and suggestions.