Hello All,

I have been struggling through a problem from long time. Can we insert
Custom Properties in the header in Excel. If yes, how??? Is it possible
only through macros & not without that?? Can anybody get me the macro
code.

My main problem is, I want to insert the date through a field/Custom
Property in the Header so that user can easily go and change the date
just by updating the field as we do in MS WORD.

Plz somebody help. Its urgent.

Thanks,
Rudra
 
J

John

Hello All,

I have been struggling through a problem from long time. Can we insert
Custom Properties in the header in Excel. If yes, how??? Is it possible
only through macros & not without that?? Can anybody get me the macro
code.

My main problem is, I want to insert the date through a field/Custom
Property in the Header so that user can easily go and change the date
just by updating the field as we do in MS WORD.

Plz somebody help. Its urgent.

Thanks,
Rudra

Rudra,
Yes you can but this is the wrong newsgroup to answer that question.
This newsgroup is dedicated to questions/issues about MS Project, a
planning and scheduling application. I suggest you try one of the many
newsgroups that deal with Excel.

John
Project MVP
 
A

Aryan

Thnx John, I by mistake posted dat query in a wrong group. Thnx nywez 4
correctin me..;)
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top