Can you lock a task?

C

Chris Marriott

Greg

Unfortunately no, there is no way to manually lock a task if you are using
Project Standard. In the standard edition there is not way to allow
read/write access to your project while preventing users from viewing any
sensitive information or preventing them from performing any specific
functions.

Project Professional / Project Server has a feature that protects actual
progress data using mangaged periods. All actual progress is entered through
a timesheet. Entries are stored in protected fields which can be synchronised
with the plan if any manual adjustments have been made.

I hope this is of some help


--
Regards


Chris Marriott
UK - EPM Consultant & Trainer
 
J

Jan De Messemaeker

..... But the PM or anybody opening the .mpp file still has access to every
task row.
 