S
SheriTingle
Hello and thanks for the help. I am using versions 2000 to 2003 for this type
of project. I need to simipy put in that a project task happens on a certain
date. No length involved. Every task will occur on a given day from 9 AM to
noon. For example I would have Task 1 on January 12 from 9-noon, then Task 2
on January 17 from 9-noon, then February 14 from 9-noon. I don't want to take
the time to figure out the length between tasks.
I know you can type in a specific date in the table view but I've heard that
can cause problems and it's always better to type in the duration and let
Project figure out the date.
Will I run into problems that anyone can foresee?
Thanks for the help! Happy 2006!
of project. I need to simipy put in that a project task happens on a certain
date. No length involved. Every task will occur on a given day from 9 AM to
noon. For example I would have Task 1 on January 12 from 9-noon, then Task 2
on January 17 from 9-noon, then February 14 from 9-noon. I don't want to take
the time to figure out the length between tasks.
I know you can type in a specific date in the table view but I've heard that
can cause problems and it's always better to type in the duration and let
Project figure out the date.
Will I run into problems that anyone can foresee?
Thanks for the help! Happy 2006!