    In the project information I have entered 5/17/2016 as Project Start Date and 9/14/2016 as Project End Date. In the Task Information I have entered series of tasks and Start as 5/17 and End as 9/14.

    As I am entering the tasks the last is completed on 7/13 and for some reason the Project Finish Date now shows 7/13 instead of 9/14. This is so weird. I have tried several times to update the project start and end date to display

    5/17 - 9/14 and the project schedule should start from start date. but then again it changes back 7/13 instead of showing 9/14.

    I want to show 9/14 as end date so when I am estimating I can tell if I will be able to meet that date or not .

    can anyone help ?
     
    samantha, Jun 25, 2016
    #1
    1. Advertisements

  2. samantha

    Kenneth Wong

    Joined:
    Sep 15, 2016
    Messages:
    5
    Likes Received:
    0
    Hi Samantha,

    It seems to me that your project will complete earlier i.e. 7/13 rather than 9/14, meaning you have successfully met your target date.

    Regards,
    Kenneth Wong
     
    Kenneth Wong, Oct 5, 2016
    #2
    1. Advertisements

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments (here). After that, you can post your question and our members will help you out.