Can you set the format in which duration is displayed in Project Web Access,
it is currently shown in days and we would like it to be displayed in hours!
regards
Dave
Dave,
If you are talking about the "My Tasks" screen, you can change that
web part by clicking the "Site Actions" at the top of the page and
choose "Edit Page". Scroll all the way to the right and click the
edit button at the top of the existing My Tasks web part and choose
Modify Shared Web Part. Scroll even further to the right, you will
see the My Tasks option settings. Go to Project Web Access and expand
it. Scroll down and you will see duration format - change that to
hours.
Hope this helps you.
KarenF