Can you start a dependent task at a certain level of completion?

D

damien

I would like to start a dependent task when it's predecessor reaches
something like 33% completion.

Is this something that Project can do?
 
B

Barbara - Austria

Hi Damien,

yes, Project can do that for you:
Open task information of your dependent task, open Predessors tab and enter
'-67%' in 'Lag' column. Does it show what you expected?

Regards
Barbara
 
J

Jim Aksel

Actually, you can start the successor activity any time you want... just key
in an actual start date and forget the logic.

To schedule this propely, it is best to do it from a forward pass
(Predecessor SS+33%). Using negative lag is not a best practice since you
really don't know when the predecessor will finish with absolute certainty.

This type of planning using indicates lack of detail in the schedule. You
really should not arbitrarily say "When A is 33% complete, I can start B."
There is more than likely some tangible event in "Task A" that can be broken
out. For example, if Task is is "Mow the lawn" and Task B is "rake leaves"
..... maybe it is best to break Task A into "Mow Front Yard" and Mow Back
Yard" ... then Task B can start immediately after the front lawn is mowed.

I give an example of using % associated with Lag on my blog. Read my white
paper about Predecessor and Successor relationships.
--
If this post was helpful, please consider rating it.

Jim Aksel, MVP

Check out my blog for more information:
http://www.msprojectblog.com
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top