I am trying to create a new calender.
When i choose tools->change working time , a window is
prompt but there is no "new" button.
i am using msp 2002 pro'
thanks for your help
 
D

Dale Howard [MVP]

Anonymous --

If your Project Server administrator has disallowed local calendars to be
used in projects, then you cannot create your own calendars. If you need a
specific calendar for your project, then you should contact your Project
Server administrator and ask him/her to create an enterprise calendar for
you.

If, on the other hand, you are your company's Project Server administrator
and are trying to create an enterprise calendar, you need to open the
Enterprise Global before doing so (Tools - Enterprise Options - Open
Enterprise Global). Hope this helps.
 