My 'Admin' projects don't show up in Adjust Actuals. Is there a way to change that??
J JenGoSto Mar 20, 2008 #1 My 'Admin' projects don't show up in Adjust Actuals. Is there a way to change that??
J JenGoSto Mar 20, 2008 #2 I actually figured this out and thought I'd share if anyone else runs into this. I just needed to look a little harder. Choose View Options within Adjust Actuals and select the 'Administrative Tasks' check box. This will include the Admin projects in the results. Thx.
I actually figured this out and thought I'd share if anyone else runs into this. I just needed to look a little harder. Choose View Options within Adjust Actuals and select the 'Administrative Tasks' check box. This will include the Admin projects in the results. Thx.