R
R23
All,
It is common to work more than 8 hours a day to Catch up or Get ahead.
Right now when a user puts in more than 8 hours in a day project server
automatically puts 8 hours on the first day and then puts 4 hours on the next
day and moves the rest of the project out. If I worked 12 hours in a single
day then it should be able to handle this. It always assumes only 8 hours a
day and moves the deadlines out. It is important for us to capture the
actual time if it is under the allocated time or over the allocated time. If
someone works extra 4 hours to get back on schedule we need to know that the
project will not be pushed out 4 extra hours but can still be completed on
time. Help!!
It is common to work more than 8 hours a day to Catch up or Get ahead.
Right now when a user puts in more than 8 hours in a day project server
automatically puts 8 hours on the first day and then puts 4 hours on the next
day and moves the rest of the project out. If I worked 12 hours in a single
day then it should be able to handle this. It always assumes only 8 hours a
day and moves the deadlines out. It is important for us to capture the
actual time if it is under the allocated time or over the allocated time. If
someone works extra 4 hours to get back on schedule we need to know that the
project will not be pushed out 4 extra hours but can still be completed on
time. Help!!