R
Richard Quinn
Hello,
I have a tricky question based around accounting for reality in a
project plan, using MS-Project. Work which is done but not directly
attributable to any of the planned tasks usually falls below my
tracking radar. The team members can never attribute 100% of their
working day to the tasks, and yet I must shoulder 100% of the cost for
a working day.
Let's assume that a project manager is given a team of 6 engineers,
plus himself, making a 7 person project team. Let's assume that all of
these people cost $50 / hr, each and every hour they work, and that
they all work 8 hrs /day on the project. Let's assume that this is a
research project, and it has a fixed duration of 14 weeks.
This gives us a fixed staffing cost of 7 (people) * 8 (hours/day) *5
(weekdays) * 14 (weeks) * $50 = $196,000. As a project manager, we
now know that, irrespective of which tasks people are assigned to, the
staffing costs will be $196.000 - unless of course the team changes or
the project duration changes.
Let's also assume that the project manager schedules tasks and assigns
people to tasks, creates a baseline, adjusts task duration, updates
task completion regularly and all the other work necessary to enable
EVA. But at the same time, he knows that he can't capture every
activity in a task, and that only 40% - 60% of an engineer's workday
will be directly attritutable to a planned task.
How can I plan the project in MS-Project, so that the total cost of
$196.000 is accurately reflected, whilst at the same time being able
to plan and analyse work which is directely attributable to a planned
task?
I was thinking of a "catch-all" task, to which each team member is
assigned as a ressource, but has a lower priority than the other
tasks, thus not interrupting them or their scheduling.
Thanks for any pointers,
-Richard
I have a tricky question based around accounting for reality in a
project plan, using MS-Project. Work which is done but not directly
attributable to any of the planned tasks usually falls below my
tracking radar. The team members can never attribute 100% of their
working day to the tasks, and yet I must shoulder 100% of the cost for
a working day.
Let's assume that a project manager is given a team of 6 engineers,
plus himself, making a 7 person project team. Let's assume that all of
these people cost $50 / hr, each and every hour they work, and that
they all work 8 hrs /day on the project. Let's assume that this is a
research project, and it has a fixed duration of 14 weeks.
This gives us a fixed staffing cost of 7 (people) * 8 (hours/day) *5
(weekdays) * 14 (weeks) * $50 = $196,000. As a project manager, we
now know that, irrespective of which tasks people are assigned to, the
staffing costs will be $196.000 - unless of course the team changes or
the project duration changes.
Let's also assume that the project manager schedules tasks and assigns
people to tasks, creates a baseline, adjusts task duration, updates
task completion regularly and all the other work necessary to enable
EVA. But at the same time, he knows that he can't capture every
activity in a task, and that only 40% - 60% of an engineer's workday
will be directly attritutable to a planned task.
How can I plan the project in MS-Project, so that the total cost of
$196.000 is accurately reflected, whilst at the same time being able
to plan and analyse work which is directely attributable to a planned
task?
I was thinking of a "catch-all" task, to which each team member is
assigned as a ressource, but has a lower priority than the other
tasks, thus not interrupting them or their scheduling.
Thanks for any pointers,
-Richard