I am wondering if there is anyway to change the baseline default saving.
Specfically I have a client who will be saving each task to the baseline and
I would like the process to be:
Tools/Tracking/Save Baseline
and here's the change. I want the Save baseline dialogue box to default to
"Selected Tasks" - currently in the "For" section it defaults to "entire
project"
Is there any way to do this? I have click the set as default button;
however, that only changes the check boxes once the radio button for
selected tasks is chosen

Thank you
Kathleen
 
J

Jack Dahlgren

Kathleen,

As far as I know, there is no way to change the default setting in that
dialog box.
Sorry.

-Jack Dahlgren
 
K

Kathleen

Thank you Jack - I was afraid of that
K

Jack Dahlgren said:
Kathleen,

As far as I know, there is no way to change the default setting in that
dialog box.
Sorry.

-Jack Dahlgren
 
M

Mike Glen

Hi ,

You could create a macro to do this, and set it up on a tool button. You
might like to have a look at my series on Microsoft Project in the TechTrax
ezine, particularly #16 on macros, at this site: http://tinyurl.com/2xbhc
or this:
http://pubs.logicalexpressions.com/Pub0009/LPMFrame.asp?CMD=ArticleSearch&AUTH=23
(Perhaps you'd care to rate the article before leaving the site, :)
Thanks.)

FAQs, companion products and other useful Project information can be seen at
this web address: <http://www.mvps.org/project/>

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top