Hi, this question came up recently "How do you change a calendar's default
weekend (Saturday-Sunday) to Friday-Saturday?" The weekends are different in
some countries around the world.
I know it can be done manually month by month by holding the control key
down, selecting the Sundays and make them working days and then repeating the
process for Friday except making them non-working days. There should be an
easy way to just say the defaults weekends are Fri-Sat vs. Sat-Sun.
Sometimes easier than it sounds.
Any help would be greatly appreciated.
 
J

Jan De Messemaeker

There IS an easy way, but it's different in 2003 vs. 2007

2003: click on the S's of Saturady and Sunday, click nondefault working
time, define working time
Then click on the T and the F in teh calendar header, click nonworking time.
Done.

2007: click Work Weeks, then details
Now you can select the days upper left: then similar to 2003

HTH

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
+32 495 300 620
For availability check:
http://users.online.be/prom-ade/Calendar.pdf
 
D

DougL

Big thanks, Jan!! Worked great.


Jan De Messemaeker said:
There IS an easy way, but it's different in 2003 vs. 2007

2003: click on the S's of Saturady and Sunday, click nondefault working
time, define working time
Then click on the T and the F in teh calendar header, click nonworking time.
Done.

2007: click Work Weeks, then details
Now you can select the days upper left: then similar to 2003

HTH

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
+32 495 300 620
For availability check:
http://users.online.be/prom-ade/Calendar.pdf
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top