change id numbers to task numbers

R

Rich Bac

if i create aprogramme with the dates out of order and then want to rearange
them to run in sequence how do I get the ID numbers to run in sequence
instead of being out of order
 
J

John

Rich Bac said:
if i create aprogramme with the dates out of order and then want to rearange
them to run in sequence how do I get the ID numbers to run in sequence
instead of being out of order

Rich,
Simple, first go to Project/Sort. Set the sort for Start date, (I assume
that's what you mean by "in sequence"), and then check the option to
"permanently renumber tasks". You may or may not want to "keep outline
structure".

John
Project MVP
 
J

Jan De Messemaeker

Hi all,

Just for the sake of completeness, when you uncheck Keep outline structure
there is no way to permanently renumber.
HTH
 
J

John

Jan De Messemaeker said:
Hi all,

Just for the sake of completeness, when you uncheck Keep outline structure
there is no way to permanently renumber.
HTH
Jan,
Good catch. Sometimes I forget the little details. Thanks for clarifying.

John
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question