Change in Project Manager

C

Chris M.

A project manager uploads a project schedule to project
server. He then becomes the PM and then is responsible
for all approvals. If someone else takes over this job
from him, how do you change it so the new person becomes
the new PM and takes over responsiblity for approving
updates to the schedule.
 
R

RLynn

To change the PM all you have to do is have the new PM
open the project and do Colloborate/Publish/Republish
Assignments. Then, check the box "Become the Manager of
these Assignments" and click "OK".

That should do it.
 
S

shadi

Hi,
first u need to make sure that the new PM can open the
that you want to change, then the new PM has to
select "Republish" and then select the "become the manager
of these tasks"
and you are done
 
Top