I have an issue when approving changes in working time
that are submitted by a resource in Web Access. When I
update them to the project through the Web Access which
them opens the Project client, the changes are applied
correctly. I save and exit. Everything looks good. But
the next time I go into the project from the Project
client, the changes are undone automatically. I have
tried this a a project manager and as an administrator.
Thanks for the help.
 