Change Order in Resource Sheet View

K

koolkat

In the Resource Sheet View it shows overallocations in RED. Is there a way
to sort so those Resources show up at the top? I have hundreds of Resources
and I'm always having to scroll up and down to find the overallocations.
 
J

Jim Aksel

With the Resource View open, you should see "All Resources" in the filter
drop down box. Select the drop down and choose "Overallocated".

Or, Project/Sort/Sort by...
Choose "Overallocated" (Descending) and then Name (Ascending). This will
bubble overalocated resources to the top and list them alphabetically.
--
If this post was helpful, please consider rating it.

Jim Aksel, MVP

Check out my blog for more information:
http://www.msprojectblog.com
 