W
Willy_comp
Despite the answers found, I think that "changing the project owner" should
be possible.
(PS : I hope that Dale Howard can influence Microsoft)
New tasks needs to arrive at the new owner because
a) the previous owner could have left the company
b) if a Programme Office prepares the initial schedule, then we do not want
to transfer the decisions of new tasks to this office, but directly to the
project manager.
regards,
Willy
be possible.
(PS : I hope that Dale Howard can influence Microsoft)
New tasks needs to arrive at the new owner because
a) the previous owner could have left the company
b) if a Programme Office prepares the initial schedule, then we do not want
to transfer the decisions of new tasks to this office, but directly to the
project manager.
regards,
Willy